Client
W.M Schlosser Company

Schedule
Started: December 2013
Ended: February 2016

Project Value
$33M

Services Provided
Safety Management Services

Baltimoree, MD

This project involves the replacement of existing underground and aboveground steel piping for gaseous oxygen with new aboveground schedule 40 stainless steel piping. Other work includes replacement of evaporators and upgrades to the instrumentation. Major trades include selective demolition, asbestos and lead abatement, removal of contaminated soils, micro-piles, concrete, masonry, miscellaneous metals, roofing, painting, cryogenic system equipment and electrical.

BMC was contracted to provide Safety Management. Responsibilities included but were not limited to the necessary materials, equipment, training, coordination, safety, supervision, and insurance.